|
Our appropriation of the year 2010
for 97% of the
investments were used.
2010 year investment fund is
53.928.095 TL. It has
been a successful period of study and appropriation
52,311,641 TL a pretty high as using
the percentage of 97% occurrence is provided.
16
substation converted from 10KV to 35KV.
Because of not to provide the system load increases of 10 kV
network, 16 substation converted from 10KV to 35KV.
In this study we removed a total of 14.75 MVA power transferred
from 10 kV to 35 kV network.In addition,during studies transformer substations
have been revisions in terms of equipment and buildings.
(Image)
81
new
substations
has been installed.
In order to meet the energy demands of new subscribers and the
voltage drop in the regions to address this problem,the total installed capacity of 64.69 MVA 81 new substation was
established.
(Image)
194,257 meters of high
voltage underground
electricity cable
has been installed.
The new high-voltage substations to the network contacts,
improvement of high-voltage network,due to the economic life of the building
completed and the rapidly growing energy transmission lines in the city's up and
threatening to transform the underground electric cable, a total of 15 companies
in our region 194,257 meters of high voltage underground electricity cables have
been installed.
(Image)
191,448 meters, low voltage underground electricity cable has been installed.
New substations of contacts with low-voltage network, low voltage problems in the
areas of partial elimination of this problem, threatening the economic life of
the overhead lines underground, to be completed and existing subscribers,191,448
meters low voltage underground electricity cable, have been installed. to meet
increasing load demands at 15 companies in our region
(Image)
Lighting plant was made 451 pieces
of galvanized steel pole.
The total 451 pieces of galvanized pole lighting facility were made to clarify lighting is poor
and the newly opened roads.
(Image)
|